Réalisation d’une nouvelle prise d’eau sur le barrage d’Idriss 1er, Maroc
Installation of a new water intake on the Idriss 1st Dam, Morocco
1 Directeur d’agence et chargé du projet Idriss 1er, Hydrokarst, 38360 Sassenage
2 Chef de division Aménagement Est, ONEE, Maroc
3 Maître d’oeuvre, ONEE, Maroc
* Corresponding author: c.caveriviere@hydrokarst.fr
L’objectif est de créer sur le barrage d’Idriss 1er une prise d’eau afin d’alimenter en eau potable les villes de Fès et Meknès. Cette prise d’eau a été créée tout en maintenant les unités de productions opérationnelles; le percement du barrage a été réalisé en eau.
Abstract
The purpose of this project is to install a new water intake on the Idriss 1st Dam to supply drinking water to the cities of Fès and Meknès. This water intake has been created while keeping the production units operational; the dam has been drilled with a filled reservoir.
© The Authors, published by EDP Sciences, 2022
This is an Open Access article distributed under the terms of the Creative Commons Attribution License 4.0, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
Current usage metrics show cumulative count of Article Views (full-text article views including HTML views, PDF and ePub downloads, according to the available data) and Abstracts Views on Vision4Press platform.
Data correspond to usage on the plateform after 2015. The current usage metrics is available 48-96 hours after online publication and is updated daily on week days.
Initial download of the metrics may take a while.