Economic Factors Analysis and Optimization Strategy of Third-generation Nuclear Power
Shanghai Nuclear Engineering Research and Design Institute Co., Ltd., 200233 Shanghai, P.R. China
* Corresponding author: fangz@snerdi.com.cn.
This paper is supported by the National Science and Technology Major Project (2017ZX06002001)
Due to the project delay, the construction price of the first unit of the two types of third-generation nuclear motor type AP1000 and EPR in China is higher than the local benchmark price of coal. If the delay is not considered, only the first unit factor is considered, the price should be between 0.48-0.49 yuan/kWh. Compared with the construction period and electricity price of solar power generation and wind power, this price still has no advantage. Therefore, the economic efficiency of nuclear power has become a key factor to determine whether nuclear power can occupy a place in the future power market and then get rapid development. In this paper, combined with the construction experience of third-generation nuclear power in China, a comprehensive economic analysis of nuclear power is carried outfrom the design requirements, equipment procurement, construction period, financing channels, operation and maintenance strategies and other factors, so as to provide direction guidance for the economic improvement of the subsequent batch construction of the third-generation nuclear power and the better participation of nuclear power in the power market competition.
© The Authors, published by EDP Sciences, 2021
This is an Open Access article distributed under the terms of the Creative Commons Attribution License 4.0, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
Current usage metrics show cumulative count of Article Views (full-text article views including HTML views, PDF and ePub downloads, according to the available data) and Abstracts Views on Vision4Press platform.
Data correspond to usage on the plateform after 2015. The current usage metrics is available 48-96 hours after online publication and is updated daily on week days.
Initial download of the metrics may take a while.