The project design of closure with cofferdam in a large reclamation project
1 Wenzhou Oufei development and Construction Investment Group Co., Ltd., Wenzhou 325025, China ;
2 Zhejiang Design Institute of water conservancy & Hydro-electric power, Hangzhou 310002, China ;
3 Zhejiang Guangchuan Engineering Consultation Co., Ltd., Hangzhou 310020, China
* Corresponding author: zjggc2007@163.com
The closure of the reclamation project generally requires that the sluice has been built and can be normally opened and closed for drainage. There is a large amount of follow-up work after closured of this project. In order to reach the safe flood control standard for the next typhoon season after the closure, reduce the flood control risk, and strive for sufficient time for the subsequent construction of the seawall, it is necessary to closure in advance under the condition that the sluice has not yet been opened. Therefore, this project demonstrated the feasibility of the closure with cofferdam based on the premise of think outside the box and theoretical calculation. The successful completion and acceptance of the reclamation project proved that the project is successful.
© The Authors, published by EDP Sciences, 2021
This is an Open Access article distributed under the terms of the Creative Commons Attribution License 4.0, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
Current usage metrics show cumulative count of Article Views (full-text article views including HTML views, PDF and ePub downloads, according to the available data) and Abstracts Views on Vision4Press platform.
Data correspond to usage on the plateform after 2015. The current usage metrics is available 48-96 hours after online publication and is updated daily on week days.
Initial download of the metrics may take a while.