Cost and Time Comparison between Corrugated Foam Mortar Technology and Girders (Study Case on Martadinata Pamulang Flyover Project)
1 Civil Engineering, Faculty of Engineering, BINUS University, Jln. K.H. Syahdan No. 9, Kemanggisan, Jakarta Barat 11480, Indonesia
2 Civil Engineering, Faculty of Engineering, BINUS University, Jln. K.H. Syahdan No. 9, Kemanggisan, Jakarta Barat 11480, Indonesia
a) Corresponding author: henry.riadi@binus.ac.id
b) caroline.sujana@binus.edu
A flyover builds to solve traffic problems in several areas. Girder often uses in flyover construction, but the use of Corrugated Foam Mortar Pusjatan is relatively new in Indonesia. This study aims to compare the cost and time of flyover construction using two different methods, Corrugated Foam Mortar and Girder. The comparison did for the same structural length of flyover 983.5 m. As a result, The Corrugated Foam Mortar method costs Rp. 46,463,841,131.40 and needs 201 days for completion, while the Girder costs Rp. 71,313,005,779.77 and needs 436 days. Based on the results, the Corrugated Foam Mortar method is 34% cheaper about Rp. 24,849,169,648.37 and 54% faster, with a time difference of 235 days faster than the girders. The cause of the biggest cost difference is material cost.
Key words: Flyover / Cost / Time / Corrugated Foam Mortar / Girder
© The Authors, published by EDP Sciences, 2024
This is an Open Access article distributed under the terms of the Creative Commons Attribution License 4.0, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
Current usage metrics show cumulative count of Article Views (full-text article views including HTML views, PDF and ePub downloads, according to the available data) and Abstracts Views on Vision4Press platform.
Data correspond to usage on the plateform after 2015. The current usage metrics is available 48-96 hours after online publication and is updated daily on week days.
Initial download of the metrics may take a while.