Improvement of boiler efficiency for Rerm-Udom sugar factory
1 Suranaree University of Technology, Institute of Engineering School of Energy and Logistics Management Engineering, Nakhon Ratchasima, Thailand
2 2Udon Thani Rajabhat University, Faculty of Technology, Department of Energy Engineering, Udon Thani, Thailand
* Corresponding author: chooprasert@gmail.com
The objective of this study is to conduct a field survey, including data collection and measurements to study the potential of energy conservation measure of Rerm-Udom sugar factory in Udon Thani. The boiler efficiency is measured and calculated using the indirect method. The results of this study show that the most significant loss of the boilers is heat loss due to exhaust gas, which is 17.2%, while the rest heat loss is around 2%. The proposed energy conservation measure to improve the performance of the boiler is to install the economizer, which helps to increase the boiler efficiency for 1.5% and helps to produce additional electricity for 2,362,800 kWh per year or 7,088,400 Baht per year. The investment cost of the economizer is 7,200,000 Baht and the maintenance cost is around 1,000,000 Baht per year. Therefore, the payback period of the energy conservation measure is 1.2 years.
© The Authors, published by EDP Sciences, 2020
This is an Open Access article distributed under the terms of the Creative Commons Attribution License 4.0, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
Current usage metrics show cumulative count of Article Views (full-text article views including HTML views, PDF and ePub downloads, according to the available data) and Abstracts Views on Vision4Press platform.
Data correspond to usage on the plateform after 2015. The current usage metrics is available 48-96 hours after online publication and is updated daily on week days.
Initial download of the metrics may take a while.