Optimization of the operation mode of the Francis turbine based on flow status analysis and stability tests
1 Luquan Wudongde Power Plant, Three Gorges Jinshajiang Yunchuan Hydropower Development Co., Ltd., 651511 Kunming, Yunnan, China
2 Datang Hydropower Science and Technology Research Institute Co., Ltd., 6100833 Chengdu, Sichuan, China
3 College of Water Resources and Hydropower, Sichuan University, 610065 Chengdu, Sichuan, China
* Corresponding author: xiexiongfei2022@163.com
To ensure the safe and efficient operation of Francis turbine units under the new situation, Wudongde Power Plant takes the No.1 unit as the research object. The variable-head stability tests and the full-flow channel numerical simulation method are applied to analyze the degree of influence on the operating conditions of Wudongde Power Plant units after the storage of water in Baihetan Reservoir. This paper scientifically divides the operating area of the units so as to guide the safe, stable, and economic operation of the turbines.
© The Authors, published by EDP Sciences, 2025
This is an Open Access article distributed under the terms of the Creative Commons Attribution License 4.0, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
Current usage metrics show cumulative count of Article Views (full-text article views including HTML views, PDF and ePub downloads, according to the available data) and Abstracts Views on Vision4Press platform.
Data correspond to usage on the plateform after 2015. The current usage metrics is available 48-96 hours after online publication and is updated daily on week days.