Improving Infrastructure Performance Using BIM (Building Information Modelling): Experimental Study of Cost Reduction in Road Planning
1 Doctoral Student of Doctoral Study on Civil Engineering, Faculty of Engineering, Sebelas Maret University, 57126 Surakarta, Indonesia
2 Department of Civil Engineering, Faculty of Engineering, Sebelas Maret University, 57126 Surakarta, Indonesia
3 Department of Informatics, Faculty of Science and Data, Sebelas Maret University, 57126 Surakarta, Indonesia
4 Department of Civil Engineering, Faculty of Engineering, Oriental Timor Lorosa’e University, 10000 Dili, Timor Leste
* Corresponding author: This email address is being protected from spambots. You need JavaScript enabled to view it.
Abstract
The productivity of the construction sector still needs to be increased by choosing effective methods. Manual method (2D) road planning takes a long time and results are less accurate. BIM (Building Information Modelling) as a new method needs to be proven for use in road planning projects. In this study, the BIM method was applied to the case study of the new road planning of Kretek-Girijati using Autocad Civil 3D software. Planning includes vertical alignment and horizontal alignment with the 2021 Geometric Road Guidelines standards. Furthermore, the volume of excavation and landfill will emerge from the model and the total cost will be known after multiplying the unit price. Some planning alternatives use BIM models compared to the initial design. There are 3 alternative designs made, featuring a shorter road trace length, more sloping, less excavation volume and pile than existing routes. The cost of the existing design is IDR 28,920,870,000.00, the most economical cost in Alternative 3 is IDR 15,697,819,300.00 with the difference in the cost of both IDR 13,223,045,900.00. It was concluded that Alternative 3 is the most economical in terms of earthworks compared to other alternatives and existing designs. These findings provide a reinforcement to use BIM methods at the road design stage.
© The Authors, published by EDP Sciences, 2025
This is an Open Access article distributed under the terms of the Creative Commons Attribution License 4.0, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
Current usage metrics show cumulative count of Article Views (full-text article views including HTML views, PDF and ePub downloads, according to the available data) and Abstracts Views on Vision4Press platform.
Data correspond to usage on the plateform after 2015. The current usage metrics is available 48-96 hours after online publication and is updated daily on week days.
Initial download of the metrics may take a while.